Charing inquiry ends… decision expected in July

The future of open countryside at Charing was debated at the public inquiry

The public inquiry into Gladman Developments Ltd’s appeal against Ashford Borough Council’s refusal to grant planning permission for 245 homes at Pluckley Road in Charing ended on Friday (April 27).
CPRE Kent been giving evidence as a Rule 6 party at the inquiry, which was held at Ashford Civic Centre. Rule 6 parties are permitted to cross-examine participants during the inquiry process.
We hope to hear the inspector’s decision in mid-July.
Points raised by CPRE Kent included:

  • The appeal site is outside the village envelope and disconnected from the village centre
  • Few people in Charing use the village train station to get to work, questioning the scheme’s sustainability
  • Increased vehicle movements and the attendant risk to both drivers and pedestrians, including children coming home from school
  • The setting of the village on the edge of the Kent Downs AONB
  • The importance of the countryside in promoting health
  • The planned development would add an unsustainable 30% to the village population
  • The site is in a flood zone so could be flooded
  • The risk of contamination to boreholes providing water to local people

For more on this story, see
here 
and
here

Monday, April 30, 2018

Comments are closed.